Tesla Optimus release dates: the complete dated record

Tesla Optimus release dates: the complete dated record
The short version

There is no Optimus release date you can act on. The consumer date currently on the record is public sales by the end of 2027, promised at Davos on January 22, 2026 with conditions attached, and the original "production ready by 2023" target was 31 months overdue as of August 7, 2026.

There is no Tesla Optimus release date. There are seven, spread across four years, and the only one aimed at consumers puts public sales at the end of 2027.

None of the seven is something you can act on today. No price page, no configurator, no waitlist, no deposit. tesla.com/optimus refuses automated requests, and no Tesla channel has ever offered a unit to a buyer. The $20,000 to $30,000 figure that circulates as a price is a target Musk named in October 2024, which is why the Optimus tracker entry files it as a claim with an empty price field.

What follows is every date, in the order it was said, so you can see which ones expired and which one is running now.

Timeline of the seven Optimus dates Tesla has named, each labelled with the month it was said: April 2022, production ready by 2023, now 31 months overdue; June 2024, limited production in 2025 with more than 1,000 units for Tesla's own use at around $30,000 retail, never announced; January 2025, roughly 10,000 robots built during 2025, with no cumulative build count ever published; January 2025, sales to third parties from 2026, with no order channel seven months in; January 2026 at Davos, sold to the public by the end of 2027, conditional, with Musk admitting six days later that no Optimus robots were doing useful work at Tesla; April 2026, a V3 reveal in the middle of the year that is five weeks late; and April 2026, production at Fremont in late July or August, a window that is open with no start announced

Every date Tesla has named

When it was said The date promised What that date produced, as of August 7, 2026
April 7, 2022 (Cyber Rodeo) Musk hoped Optimus would be "production ready by 2023" 2023 ended with the Gen 2 demo video. No production line
June 2024 Limited production begins in 2025, more than 1,000 units for Tesla's own use, around $30,000 retail No production start was ever announced
January 2025 (Q4 2024 call) "The normal internal plan calls for roughly 10,000 Optimus robots to be built this year" Tesla has never published a cumulative build count, then or since
January 2025 (same call) Sales to third parties, rather than internal use only, start in 2026 Seven months into 2026 there is no order channel of any kind
January 22, 2026 (Davos) Sold to the public by the end of next year, meaning the end of 2027, conditional on "very high reliability, very high safety" and a wide range of functionality Six days later Musk said no Optimus robots were doing useful work at Tesla
April 22, 2026 (Q1 call) V3 revealed "probably middle of this year" Mid-year passed five weeks ago with no reveal
April 22, 2026 (Q1 call) Production starts at Fremont in "late July or August" The window is open as this is written. Tesla has not said it started

The 2022 and 2024 rows trace to the timeline on Optimus's Wikipedia entry. The January 2025 rows come from Electrek's report on the Q4 2024 call, where Musk gave the 10,000 figure and immediately hedged it: exactly 10,000 by December, probably not, "several thousand," yes. The Davos promise is Engadget's same-day write-up, and the admission six days later is Electrek, January 28, 2026. Both April rows come from Electrek's coverage of the Q1 2026 earnings call.

Three different release dates wearing one word

Most Optimus headlines flatten three separate milestones into "release date," and they are years apart.

Production start. Robots come off a line. They belong to Tesla. Nobody outside the company can obtain one. This is the milestone with the live date on it, late July or August 2026, and it is the one most likely to be reported as Optimus launching.

Sale to other companies. Musk put this in 2026 back in January 2025. Enterprise customers, purchase orders, deployments in someone else's factory. No such sale has been announced.

Sale to the public. This is the one a reader searching for a release date usually means, and the only date on the record for it is the end of 2027, from Davos. The conditions attached to that promise get dropped in the retelling: Musk tied it to very high reliability, very high safety and a wide range of functionality, all three assessed by Tesla. The session is on the record in full, from the organiser.

The World Economic Forum's own recording of the January 22, 2026 session with Larry Fink, where the only consumer date in the table above was said out loud: "By the end of next year I think we'd be selling humanoid robots to the public," followed immediately by the reliability, safety and functionality conditions that the retellings drop.

A robot rolling off a Fremont line in August is compatible with no consumer ever buying one. The dated archive of Musk's robot claims tracks the wider pattern of restated targets; this page tracks only the calendar.

How far each one has slipped

Milestone First date given Where it stands, August 7, 2026 Overdue by
Production ready 2023, said April 2022 Production start now scheduled for late July or August 2026, unconfirmed 31 months past the end of 2023
Limited production, 1,000-plus units 2025, said June 2024 No start announced, no unit count published 7 months past the end of 2025
Roughly 10,000 robots built during 2025, said January 2025 Outcome never disclosed Unmeasurable, which is its own answer
Sales outside Tesla 2026, said January 2025 No order channel. The consumer version of this promise now reads end of 2027 Not yet late. Five months left
V3 reveal middle of 2026, said April 2026 Not revealed. Latest generation shown in public is v2.3, in London and Berlin in December 2025 5 weeks

The V3 row is worth watching more closely than the others, because Tesla has tied the reveal to production start: the generation gets unveiled when the line is close. That makes it the tell. If the third quarter closes with no V3, the production window that opened this month was optimistic as well.

What August 2026 actually looks like

Tesla did real physical work this year, and everything verifiable from outside was done to the building rather than to the robot. The Fremont general assembly line that built the Model S and X came out to make room, a teardown Teslarati reported on July 10, 2026 as finishing in 46 days, with full-scale output on the converted line expected in late July or August. That line has been described as designed for a million robots a year. A second line at Gigafactory Texas is aimed at ten million a year from 2027, a figure Optimus lead Ashok Elluswamy restated on July 30, 2026 when he corrected a smaller number upward.

Set those capacities against the count of Optimus units Tesla has ever said it built: none. Not a cumulative figure, not a monthly one, not once in five years. Figure, a far smaller company, published "more than 350" Figure 03s built by April 29, 2026, which is the comparison drawn out in Figure vs Tesla Optimus.

Musk has also been managing expectations downward in public. On the April call he declined to give any 2026 production target at all, said early output would be "quite slow," and described a line whose speed is set by the least lucky and slowest of roughly 10,000 unique parts. On July 2 he pushed back on the fan theory that Tesla is secretly further along, warning that manufacturing would be extremely slow at first, per Electrek's running Optimus guide. Neither statement is a slip on its own. Both are the sound of a company lowering the bar it will be measured against in January.

Four things that would turn a date into a product

Falsifiable, in rough order of how soon each could plausibly happen.

  1. A V3 reveal with a spec sheet. Height, weight, payload, runtime, degrees of freedom. Tesla has published no spec sheet for the generation it is tooling for.
  2. A cumulative build count. Any number of robots produced, stated by Tesla, with a date on it.
  3. A sale to someone. A named external customer, a purchase order, a deployment in a building Tesla does not own.
  4. A price and a way to pay it. The $20,000 to $30,000 range has been a target since October 2024. It becomes a price the day there is a checkout behind it.

Until at least the first two land, the sensible reading of any new Optimus date is that it describes progress at a factory. If you want a walking humanoid in your house on a timescale you can plan around, the current options are covered in humanoid robots you can actually buy in 2026, and the year's wider promised-versus-delivered scorecard is in what actually shipped in 2026.

The next scheduled moment for any of this to move is Tesla's third-quarter results, which in recent years have landed in the back half of October. Two dates will be sitting on the table by then: a V3 reveal that was due in June, and a production start that was due this month.